PROJECT 1 : SKELETAL CONSTRUCTION (TEMPORARY BUS SHELTER)

OBJECTIVE
  • To create an understanding of skeletal structure and its relevant structural components.
  • To understand how a skeletal structure reacts under loading.
  • To demonstrate a convincing understanding of how skeletal construction works.
  • To be able to manipulate skeletal construction to solve an oblique design problem.

LEARNING OUTCOME
After this project, we were able to:
  • Apply construction system in design.
  • Recognize the implication of construction systems in design.
  • Analyse the issues of strength, stiffness and stability of structures including modes of structural systems, forces, stress and strain and laws of static.

SPECIFICATION
  • SCALE-Your bus shelter should be constructed to accommodate 5-6 people (1:20). 
  • Max height is 600mm. Max base size is 400mm x 800mm
  • CONSTRUCTION- It should demonstrate the knowledge of skeletal frames and its joints. It must clearly define all building components such as roof, column, walls and floor. The structure should be elevated at least 50mm from the ground.
  • JOINTS-The joints should be constructed to reflect actual joints. For example, if a group chooses recycle steel materials for the frame, the joints should be made to resemble bolts and nuts etc. You are not allowed to use inappropriate materials for joints such as rope for steel.
  • MATERIALS- You are encouraged to use recycled materials such as newspaper, pet bottles, cans, etc. However, the chosen materials must relate to its function. For example, roofing materials should not be made from newspaper.
  • OTHER DESIGN CONSIDERATIONS- This is just a minor component however; the shelter should be light and portable. o Resistant to weather. o Allows easy access in and out from the shelter o Shelter SHOULD NOT BE OVERLY DESIGN and must conform to the design criteria.
  • TEST-The completed shelter will be tested to withstand lateral forces. In actual situation, from wind and earthquakes or any horizontal forces.
  • Analysis on the design, construction progress and test results are to be provided in the form of an A3 bound report.
  • Students are encouraged to use annotated sketches / diagrams to explain the construction, joints, forces, structural movement experienced during the testing of the shelter.
  • Photographs of the shelter should also be incorporated into the presentation report. 

PROCESS OF CONSTRUCTION































FINAL BOARD & MODEL